Cost Sharing Issues
Key Issues
58. The issue of sharing of the costs for utility related
activities in the roading corridor has been an ongoing issue for
both road controlling authorities and utilities for some time.
59. Issues that have arisen from consultation:
Is there inconsistency with the provision of
cost sharing arrangements in the legislation?
Is there a lack of an accepted payment
formula/ratio (depending on who wants the works, who owns them and
who benefits from them)?
Is there agreement on the categories of
chargeable services or on the principles for charging/not charging?
Discussion
60. There are two separate issues within the broader issue of
cost sharing that will be addressed in this section:
- Cost sharing arrangements for the works
- Auxiliary service charges (e.g. inspections).
Cost Sharing Arrangements for Works
61. The NZUAG
has identified 4 key issues in relation to charging for services in
the road corridor as follows:
- Definition of the range of chargeable services and the
beneficiaries;
- Establishment of fair and reasonable principles for charging
and not charging;
- Definition of how charges are calculated and applied (i.e.,
application of fair ratios, e.g., 50:50 provisions); and
- Avoidance of duplication of charges.
62. For the relocation of utilities caused by another party's
work within the road, it could be argued that the full cost should
fall with the party initiating the work since it represents a cost
of the work they are doing, and is not being caused by the utility
asset owner. With 50:50 provisions there are circumstances where it
may not be fair, e.g., in some cases a relocated utility will result
in a brand new section of the network and the original network may
have been at the end of its economic life.
63. The opposite of this is where an asset may have only recently
been installed, and the utility has sought the approval of the road
controlling authority and gained confidence that the road would not
be altered in the near future, only to find that it is required to
be shifted.
64. Table 2 illustrates the various statutory provisions for cost
sharing for utility works within the road.
Table 2: Statutory Provisions
for Cost Sharing for Utility Works within the Road| Legislation | Relevant Section | Party to Bear the Costs | Proviso |
| Transit New Zealand Act 1989 | s54 (removal of roadside structures) | 50/50 equal split between
RCA and
utility | |
| Electricity Act 1992 | s24 | Electricity operator to meet reasonable costs of local
RCA for
processing notices and supervising works | Does not apply to fittings |
| s33 | Who causes works pays (including for relocation) | Utility owner not entitled to claim for betterment of
utility |
| If required by
RCA - RCA
to pay for work, but Utility operator must pay for
fittings | Utility owner not entitled to claim for betterment of
utility |
| | s54 of Transit New Zealand Act 1989 shall not apply
to electricity and gas operators |
| Gas Act 1992 | s24 | Gas operator to meet reasonable costs of local
RCA for
processing notices and supervising works | Does not apply to fittings |
| s34 | Who causes works pays (including for relocation) | Utility owner not entitled to claim for betterment of
utility |
| If required by
RCA - RCA
to pay for work, but Utility operator must pay for
fittings | Utility owner not entitled to claim for betterment of
utility |
| | s54 of Transit New Zealand Act 1989 shall not apply
to electricity and gas operators |
| Telecommunications Act 2001 | s148 (alteration to line or road) | Party that makes request to meet costs | Network operator not entitled to be paid the cost of any
improvement to the line |
| Local Government Act 2002 | s198 | "Development contribution" may be required by local
authority for issuing of resource or building consents, or
service connections | s197: Does not include the pipes or lines of a network
utility operator |
65. Section 54 of the Transit New Zealand Act 1989 (the removal
of roadside structures) considers that where any structure has been
erected upon, under or over any road by any utility authority, "the
reasonable costs, subject to any agreement to the contrary, incurred
by a utility authority in removing any structure shall be borne by
the controlling authority and the utility authority in equal
shares". A controlling authority or utility authority may apply to
the District Court to vary the proportions in which the costs and
the compensation shall be borne, and the District Court's decision
shall be binding. Within the Act a "utility authority" means the
Crown, a local authority, company or person lawfully authorised to
construct, maintain, utilise or use the structure. Therefore this
applies to Transit New Zealand Ltd (if they are a utility
authority), local authorities (e.g. water, waste water, storm water)
or utility owner.
66. Section 148 of the Telecommunications Act 2001 notes that if
there is an alteration to a line on a road (requested by the owner),
the person who makes the request is to meet the costs. The network
operator may require the person who makes the request to pay the
cost of the alteration. However, the network operator is not
entitled to be paid the cost of any improvement to a line. The
Telecommunications Act does not seem to provide an explicit
provision for an "agreement to the contrary", but this could be
covered by Section 54 of the Transit New Zealand Act 1989. As the
Telecommunications Act does not provide any clause that negates
Section 54 of the Transit New Zealand Act, it applies.
67. Section 33 of the Electricity Act 1992 indicates that the
costs of work required by a
RCA shall be paid by the person that requires the work to be
done. However, where a RCA
requires the work (as defined in the Transit New Zealand Act 1989),
the owner of the works shall pay for the costs of all fittings and
the owner of the works are also required to pay for increased costs
or where the works are reconstructed to specifications different
from those of the original works. This section is subject to any
agreement between the persons requiring the work to be done and the
owner of the works, i.e. alternative agreements are possible.
68. Section 24 of the Electricity Act 1992 (construction or
maintenance of works in the road) notes that a local authority (or
other body with road jurisdiction) may require the electricity
operator to meet the reasonable costs and expenses of the local
authority (or other body with road jurisdiction). Under the
provisions of the Gas Act 1992, where a local authority requires
work to be relocated this shall be paid for by the person that
requires the work to be done. However, if it is a controlling
authority (as defined in the Transit New Zealand Act 1989), the cost
of fittings shall be paid for by the owner and increased costs or
costs as a result of different specifications shall be paid for by
the owner of the works. The provision for an alternative agreement
is also available under the Gas Act 1992. The appeal provision
against these provisions is by reference to an arbitrator under the
provisions of the Arbitration Act. Both the Electricity Act 1992 and
the Gas Act 1992 specifically provide that Section 54 of the Transit
New Zealand Act 1989 shall not apply to electricity and gas.
69. The Railways Act 2005 provides no mechanism for cost sharing
for works in the road corridor. However, for utility access to the
rail corridor, section 75 in the Railway Act 2005 gives the railways
premises owner the right to set "reasonable" charges for granting
access to works, that a charge for "a deed" or "agreement" must be
"reasonable" and, similarly, access cannot be denied without
"reasonable" grounds. In addition, section 75(7) states that the
rental "from an easement granted to a public body on, over, or under
a railway at a level crossing may be no more than nominal." The
requirement for permission is imposed in section 75 "despite
anything in any other Act", which negates rights under the other key
infrastructure Acts, including the Gas and Electricity Acts 1992.
70. Under the Railway Safety and Corridor Management Act 1992
there was no restriction on the conditions that could be specified
by a rail operator. Therefore, if a charge was imposed there were no
criteria of reasonableness. Under the Railways Act 2005, this has
been amended to ensure that any charge imposed must be "reasonable"
(clause 75(4) of the Act).
71. Finally, section 198 of the Local Government Act 2002
indicates that a local authority may require a development
contribution to be made when it grants a consent (resource and
building) or an authorisation for a service connection. Development
contributions may be required in relation to developments if the
effect of the developments is to require new or additional assets or
assets of increased capacity and, as a consequence, the territorial
authority incurs capital expenditure to provide appropriately for
reserves, network infrastructure or community infrastructure. Under
section 197, it "does not include the pipes or lines of a network
utility operator", however, this may mean that it could still cover
other utility assets such as cellular network towers, cabinets, or
letter boxes, for example.
72. In terms of non-statutory activity, the New Zealand Committee
for the Co-ordination of Power and Telecommunication Systems (NZCCPTS)
has produced a guide which sets down principles for determining the
apportionment of costs between electricity and telecommunications
network operators when cases of earth potential rise (EPR) hazard,
induction hazard or interference to telecommunication networks
require investigation and remedial action, and incur expenditure by
either or both parties.13
The principles are aimed at achieving resolution of issues by
agreement, thus avoiding costly litigation.
73. In 2004 the
NZUAG
carried out a survey of RCAs
to help gather information on charging between
RCAs and utilities
as part of the Road Opening and Service Location processes. The
survey provides a good indication of current practice and the
NZUAG
proposes to carry out further work on this issue, in particular the
development of a Guideline to outline current legislative provisions
and best practice for the various charging and cost relationships
between utilities and road controlling authorities. In particular
the Guideline could:
- provide legal clarification of whether the Transit New Zealand
Act (section 54) applies to local authorities or not.
- explain the current legislative provisions for
RCAs and utilities
in plain language.
- discuss the advantages and disadvantages of cost sharing -
from the perspective of the party initiating the work paying the
full cost, 50:50 provisions, and the cost of the utility paying
all the work.
- provide case studies of "agreements to the contrary" for
different approaches.
74. Another issue is the long term damage of utilities to the
road asset. RCAs
note that there is a need to consider fair apportionment of the true
whole of life costs.
Cost Sharing Arrangements for Auxiliary
Charges
75. A further issue to consider is the charging for auxiliary
service costs by local authorities to utility operators. This covers
charges for expenditure that local authorities incur in their duty
to inspect and audit utility network additions, maintain a register
of utility network locations, ensure traffic safety, and ensure the
return of the road to a state of roadworthiness post utility works.
Currently, only some local authorities charge for these services,
creating a perceived imbalance of fairness. A consequence is that
extra charges create a disincentive for utility operators to
disclose locations of networks to local authorities.
76. While this is an issue causing concern, the Ministry believes
that local government and industry stakeholders are the more
appropriate parties for discussing and implementing remedies to
achieve consistency and fairness.
Questions to Consider
77. The Ministry offers no proposals for this issue at this
stage. Instead the Ministry calls for submissions on the following
questions:
What problems have respondents experienced with
cost sharing arrangements for utility work within the road corridor?
Is there good reason for the legislative
differences for cost sharing arrangements?
Should the legislation be consistent?
What solutions do respondents propose as
providing the most balanced and effective outcome for resolving
legislative inconsistency for cost sharing arrangements for utility
work within the road corridor?
What solutions do respondents propose for
ensuring the fair apportionment of the true whole of life costs of
utility works to the road asset?
Back to Top