Summary Table
The following table summarises the main findings of the report and lists generation opportunities that have been identified in the course of this study in terms of:
- Capacity (MW)
- Estimated Annual Output (GWh)
- Year On Line with and without constraints imposed by RMA Process
- Ease of Establishment (index 1 to 5)
- Estimated Capital Cost $m
- Estimated Operating & Maintenance Cost (p.a. $m)
- Estimated Cost of delivered energy (c/kWh)
- Relative Impact of Constraints
The cost estimates contained in the following table are generic, based on typical industry indices and should not be regarded as precise. The costs given are in 2003 New Zealand dollars, at a NZ/US$ exchange rate of 0.55, and provide a measure of comparative costs of different generation options and reflect certain assumptions.
Costs per kWh take into account typical load factors for non-thermal plant (hydro, geothermal and wind). For thermal plant, where the load factors is some cases may be very low for peaking plant (but cannot realistically be predicted), they take into account fuel and O&M costs but just assume the capital cost is recovered at 10% per annum without taking into account financing costs. For the non-thermal plant, the costs per kWh are the long term prices at which the projects are considered to be viable. They do therefore take into account project financing and profit, but, as stated above, do not include up-front establishment costs, which could be significant in a full financial analysis. Further details regarding the assumptions made in establishing these costs are included in Appendix B of this report.
The summary table also includes a relative assessment of applicable constraints on a Low/Medium/High basis relating to:
- The Resource Management Act process
- Fuel/Energy Resource constraints
- Transmission constraints
- Environmental constraints
The most encouraging aspect is that the existence of adequate energy resources in New Zealand is not a constraint on achieving sufficient capacity to provide security in the short term, with environmental impacts that most New Zealanders would consider to be acceptable, when compared with the alternatives.
At the present time, there are existing and potential constraints in the high voltage transmission system that are obstacles to new generation in some areas of the country. These are discussed further in Section 4 of the report.
Air quality and noise are issues for any generation close to urban areas.
The progress of many proposed geothermal and hydro development projects is constrained by the consent process. In many cases, the assessed environmental impact of these projects is low.
Summary
| Potential MW (Ignoring time required for normal consent process) |
Year On-Line w/o RMA | Sub- total | Geothermal | Indigenous Gas | Cogeneration | Wind | Hydro | Emergency Generators | Gas / Distillate Turbines | Combined Cycle Gas Turbines1 |
| 2003 | 640 | 10 | 116.5 | 8.5 | 0 | 4 | 76 | 420 | 0 |
| 2004 | 460 | 146 | 60 | 20 | 36 | 0 | 0 | 200 | 0 |
| 2005 | 930 | 125 | 15 | 40 | 155 | 150 | 0 | 40 | 400 |
| 2006 | 620 | 75 | 0 | 0 | 0 | 144 | 0 | 0 | 400 |
| 2007 | 270 | 150 | 0 | 0 | 0 | 117 | 0 | 0 | 0 |
| 2008 | 490 | 0 | 0 | 0 | 0 | 485 | 0 | 0 | 0 |
| 2009 | 260 | 0 | 0 | 0 | 0 | 262 | 0 | 0 | 0 |
Total (approx MW) | 3670 | | | | | | | | |
Opportunity
| Ref. | | Potential Capacity (MW) | Ann. Output2 (GWh) | Time to On-Line | Year On-Line | Ease of Est. 1 = easy 5 = difficult | Capital Cost $m | O&M Cost p.a. $m | Est. Cost3 c/kWh | Constraints (Low-Med-High + = pos. envir. benefit) |
with RMA months | w/o RMA months | with RMA | w/o RMA | RMA | Fuel / Resource | Transmission | Environmental |
| 1 | Poihipi Geothermal - immediate option | 10 | 80 | >60 ? | 0 | 2012 | 2003 | 1 | 0 | 0.2 | <1 | M | | 0 | L |
| 2 | Emergency Generators - Auckland | 40 | 130 | 3-4 | 1 | 2003 | 2003 | 1 | 0 | | 15 | | | | |
| 3 | Emergency Generators- Wellington | 16 | 65 | 3-4 | 1 | 2003 | 2003 | 1 | 0 | | 15 | | | | |
| 4 | Emergency Generators - Christchurch | 20 | 80 | 3-4 | 1 | 2003 | 2003 | 1 | 0 | | 15 | | | | |
| 5 | Te Rapa Dairy - cogen | 3.5 | 27 | 3-6 | 1-3 | 2003 | 2003 | 1 | 0.1 | | 5-10 | N/a | H | L | L |
| 6 | Mangahao Hydro (committed) | 4 | 5 | 2 | 2 | 2003 | 2003 | 1 | committed | | 6 | | | | |
| 7 | Auckland Hospital Cogen (committed) | 5 | 40 | 6 | 6 | 2003 | 2003 | 1 | committed | | 5-6 | | | | |
| 8 | Southdown | 40 | 35-70 | 6-9 | 3 | 2004 | 2003 | 1 | 40 | 1 | 5-10 | | | | |
| 9 | Otahuhu A (Double ending) | 50 | 44-90 | 6-9 | 3 | 2004 | 2003 | 1 | 5-10 | 0.5 | 15 | | | | |
| 10 | Degussa, Gas engine | 1.5 | 12 | 6-9 | 3 | 2004 | 2003 | 1 | 2.5 | 0.15 | 6-13 | L | L | L | L |
| 11 | Stranded Gas Total - gas engines - various sites | 60 | 500 | 6-9 | 3-4 | 2004 | 2003 | 2 | 76 | | 6-13 | | | | |
| 12 | LandFill Gas total - gas engines - various sites | 25 | 200 | 6-9 | 3-6 | 2004 | 2003 | 2 | 18 | | 5-10 | | | | |
| 13 | Sewage Gas/Biogas - various locations | 20 | 150 | 6-9 | 3-6 | 2004 | 2003 | 2 | 30 | | 5-10 | | | | |
| 14 | Gas Turbines (Whirinaki or elsewhere) 2003 | 200 | 175-350 | 6-9 | 3-4 | 2004 | 2003 | 1 | see App A | | 15-25 | | | | |
| 15 | Power Barge | 90 | 700 | 6-9 | 4-6 | 2004 | 2003 | 1 | 20-60 | | 15-25 | | | | |
| 16 | Kawerau GT | 40 | 35-70 | 6-9 | 3-6 | 2004 | 2003 | 2 | 45 | 1 | 15-25 | | | | |
| 17 | Ohaaki Deep Drilling Geothermal | 50 | 420 | 6-9 | 6-9 | 2004 | 2004 | 1 | 26 | 2.5 | 2-3 | 0 | | 0 | M |
| 18 | Coal Seam Methane - Various sites - 2003 | 10 | 160 | 6-9 | 6-9 | 2004 | 2003 | 2 | | | 8-10 | | | | |
| 19 | Poihipi Geothermal - steam interconnect | 28 | 230 | 60 ? | 6-12 | 2008 | 2004 | 1 | 26 | 1.5 | 2-3 | M | | 0 | L |
| 20 | Gas Turbines (Marsden A) 2004+ | 200 | 219-438 | 12-18 | 6-12 | 2005 | 2004 | 1 | see App A | | 15-25 | | | | |
| 21 | Refinery Cogeneration | 20 | 150 | 12-18 | 12 | 2005 | 2004 | 2 | 25 | 1.5 | 7 | L | L | L | M |
| 22 | Kawerau Wellhead Geothermal | 10 | 80 | 36 ? | 6-12 | 2006 | 2004 | 2 | 33 | 0.8 | 6 | M | | | M ? |
| 23 | Other Wellhead Geothermal | 12 | 90 | 36 ? | 6-12 | 2006 | 2004 | 3 | 33 | 1 | 5-6 | H | | ? | L |
| 24 | Kawerau Binary Geothermal | 5 | 40 | 12 | 12 | 2005 | 2004 | 1 | 13 | 0.3 | 2-3 | L | | | + |
| 25 | Rotokawa wellhead Geothermal | 5 | 40 | 36 ? | 12 | 2006 | 2004 | 2 | 22 | 0.4 | 5-6 | M | | | L |
| 26 | Rotokawa bottoming Geothermal | 3 | 20 | 12 | 12 | 2005 | 2004 | 1 | 6 | 0.2 | 3 | L | | | 0 |
| 27 | Mokai bottoming Geothermal | 8 | 60 | 18 | 12 | 2005 | 2004 | 2 | 16 | 0.6 | 3 | | | | |
| 28 | Ohaaki bottoming Geothermal | 10 | 80 | 12 | 12 | 2005 | 2004 | 1 | 20 | 0.9 | 3 | L | | 0 | 0 |
| 29 | Tararua Wind Farm | 36 | 125 | 14 | 14 | 2004 | 2004 | 1 | 60 | 2.4 | 6 | L | L | L | L |
| 30 | Wairakei Binary Geothermal | 15 | 120 | 12 | 12 | 2004 | 2004 | 1 | 35 | 1.1 | 2-3 | 0 | | 0 | + |
| 31 | Hau Nui Wind Farm - expansion | 5 | 17 | 18 | 18 | 2005 | 2005 | 1 | 8 | 0.2 | 6 | L | L | L | L |
| 32 | Reporoa Geothermal | 40 | 330 | > 60 ? | 12-48 | 2012 | 2005 | 4 | 125 | 3 | 4-5 | H | | ? | L |
| 33 | Coal Seam Methane - Various sites - 2004+ | 60 | 800 | 18-24 | 18-24 | 2005 | 2004 | 2 | | | 6 | | | | |
| 34 | Ngawha Geothermal | 20 | 160 | 60? | 18 | 2012 | 2005 | 4 | 63-72 | 1.2 | 3-5 | H | L | L | M |
| 35 | Kawerau Central Geothermal | 20 | 170 | 36 ? | 18 | 2007 | 2005 | 3 | 65 | 1.3 | 3 | M | L | L | M ? |
| 36 | Mokai I expansion Geothermal | 30 | 250 | 18 | 18 | 2005 | 2005 | 1 | 102 | 1.5 | 3 | 0 | L | M | L |
| 37 | Tauhara Geothermal | 15 | 120-160 | 18 | 18 | 2005 | 2005 | 1 | 71 | 1.6 | 3-4 | 0 | L | 0 | H |
| 38 | Kiwi Dairies (cogen) | 40 | 320 | 24 | 24 | 2005 | 2005 | 1 | 60 | 3 | 6 | L | H | H | L |
| 39 | Kiwi Dairies (peaker) | 40 | 35-70 | 24 | 24 | 2005 | 2005 | 2 | 40 | 1 | 9 | L | H | H | L |
| 40 | Kapuni | 15 | 80 -160 | 24 | 24 | 2005 | 2005 | 2 | 25-50 | 1-3 | 7-10 | L | H | H | L |
| 41 | SI - Wind Farm | 60 | 400 | 30 | 24 | 2006 | 2005 | 1 | 100 | 4 | 6 | L | L | L | L |
| 42 | Manawatu Wind Farm | 90 | 550 | 30 | 24 | 2006 | 2005 | 1 | 140 | 5.6 | 6 | L | L | L | L |
| 43 | Tekapo B Upgrade | 20 | 50 | n/a | 24 | 2005 | 2005 | 1 | 10 | 1 | 5 | L | L | L | L |
| 44 | Manapouri Discharge + Uprate | 100 | 100 | 48 | 0 | 2007 | 2005 | 1 | 0 | 0 | 0 | L | L | 0 | L |
| 45 | Huntly E3P | 400 | 2980 | 24 | 24 | 2005 | 2005 | 3 | 500 | | 6 | | H | L | M |
| 46 | Hawea 30MW scheme | 30 | 120 | 24 | 24 | 2005 | 2005 | 1 | 90 | 0.4 | 5 | L | L | L | L |
| 47 | TCC 2 or Otahuhu "C" | 400 | 2980 | 36 | 36 | 2006 | 2006 | 3 | 500 | | 6 | | H | M | M |
| 48 | Wairau Valley Hydro | 100 | 500-550 | 42 | | 2006 | 2006 | 3 | 300 | 1 | 6 | M | L | L | L |
| 49 | Rotokawa II Geothermal | 75 | 620 | 48 ? | 36 | 2010 | 2006 | 3 | 195 | 5 | 3-4 | M | L | L | M |
| 50 | Pukaki - Hydro | 44 | 20 | 36 | 36 | 2006 | 2006 | 2 | 100 | 1 | 6.5 | L | L | M | L |
| 51 | Dobson Hydro | 57 | 270 | 48 | 36 | 2008 | 2007 | 3 | 170 | 0.8 | 6.5 | M | L | L | L |
| 52 | Putauaki Geothermal | 75 | 420-830 | 60 ? | 36-48 | 2008 | 2007 | 3 | 150-255 | 4-8 | 3-5 | M | L | L | M |
| 53 | Ngatamariki Geothermal | 75 | 420-830 | > 60 ? | 48 | 2012 | 2007 | 5 | 125-230 | 4-6 | 2-5 | H | L | M | M |
| 54 | Hawea 60MW scheme | 60 | 315 | 48? | 48 | 2008 | 2007 | 2 | 160 | 0.6 | 6.5 | M | L | M | L |
| 55 | Aqua Stage 1 | 262 | 1600 | 60 | | 2009 | 2009 | 3 | 600 | 2-3 | 5 | M | L | M | L |
| 56 | Luggate | 265 | 1277 | 72 | | 2010 | 2008 | 2 | 663 | 2 | 5-6 | M | L | M | L |
| 57 | Queensbury | 220 | 1060 | 84 | | 2010 | 2008 | 1 | 550 | 2 | 5-6 | M | L | M | L |
| 58 | Aqua Stage 2 | 262 | 1600 | 90 | | 2012 | 2012 | 3 | 600 | 2-3 | 5 | M | L | M | L |
Erratum: Amendments to Power Generation Summary Table
| Ref. | Opportunity | Potential Capacity (MW) | Ann. Output4 (GWh) |
| 6 | Mangahao Hydro (committed) | 4 | 22 |
| 41 | SI Wind Farm | 60 | 236 |
| 42 | Manawatu Wind Farm | 90 | 354 |
| 50 | Pukaki | 44 | 120 |
| 56 | Luggate | 90 | 435 |
| 57 | Queensbury | 180 | 870 |