Ministry of Economic Development Home| Contact MED|


 
 
 

Links to this page were:

Section Subnavigation Links:

7. Developing the Scenarios


Project Aqua: An Evaluation of the Economic Impact

Concept Consulting Group
[ Last Updated 22 December 2005 ]


7.1 Approach

To establish the likely economic impact of Project Aqua we have developed and simulated two scenarios, one where Project Aqua is included and another where Project Aqua is excluded. We have developed the two scenarios using the following approach:

  • The supply development options discussed in Section 6 have all been referenced to Haywards to allow ranking and comparison;
  • For each scenario, supply development options have been scheduled to meet rising demand in "merit" order according to cost, taking into account committed (or highly likely) options and possible project lead times;
  • To develop each scenario we have used a quarterly supply and demand "energy balance" model to establish likely system operation across a range of inflow years covering the full spectrum from "wet" to "dry";
  • A "security of supply" criterion has been adopted to establish the timing of new plant options. This is achieved by simulating dry years and timing the development schedule to allow for similar levels of thermal utilisation and "moderate" but not "excessive" running of New Plymouth and Whirinaki on oil;
  • The likely pattern of running and calculation of fuel consumption is established across the full pattern of inflow sequences.

7.2 With Aqua Scenario

The new generation investment schedule for the "with Aqua" scenario is outlined in Figure 5. The following factors are worthy of note:

  • Committed or "highly likely" projects have been included up to and including 2005;
  • The Genesis Power e3p CCGT project has been included in 2006;
  • Hydro efficiency, hydro enhancement and small scale hydro projects totalling 87MW have been included at regular intervals over the period to 2020;
  • Cogeneration projects totalling 160MW have been included at regular intervals over the period to 2020;
Figure 5: New Generation Investment Schedule - With Aqua
Year Owner Scheme Rated Capacity (MW) Economic Haywards Price (c/kWh)
2003Mighty River Power Rotokawa Geothermal Plant Expansion 4 Committed or Highly Likely
Auckland Hospital Cogeneration 5
2004Trustpower Tararua Wind Farm Stage II 36
Government Whirinaki OCGT Dry Year Reserve 155
Genesis Power Huntly Gas Turbine 40
2005 Meridian Energy Manapouri Hydro Scheme Re-runnering 16
Genesis Power Hau Nui Wind Farm Expansion 8
Contact Energy Wairakei Geothermal Plant Expansion 10
Tuaropaki Trust Mokai Geothermal Plant Expansion 40
Meridian Energy Te Apiti Wind Farm 85
Various Cogeneration / Other 5
2006 Genesis Power Huntly e3p CCGT400 5.9
Top Energy Ngawha Geothermal Plant Expansion 20 5.5
Various South Island Hydro Efficiency Projects 20 5.0-6.0
Various Cogeneration/Other 5 5.0-6.0
2007 Various Small Scale Hydro Projects 1 8 5.0-6.0
Various North Island Hydro Enhancements 20 5.0-7.0
Various Cogeneration / Other 5 5.0-6.0
2008 Meridian Energy Aqua Hydro Scheme Trubine 1 93 6.1
Various Cogeneration / Other 5 5.0-6.0
Putauaki Trust Kawerau II Geothermal Plant 50 5.8
2009Meridian Energy Aqua Hydro Scheme Turbines 2&3 186 6.1
Various Cogeneration / Other 5 5.0-6.0
2010Various Cogeneration / Other 5 5.0-6.0
Meridian Energy Aqua Hydro Scheme Turbine 4 83 6.1
2011Various Cogeneration / Other 5 5.0-6.0
Meridian Energy Aqua Hydro Scheme Trubines 5&6 166 6.1
2012 Various Cogeneration / Other 5 5.0-6.0
2013 Various Cogeneration / Other 20 6.0-6.5
Various Geothermal Expansion 10 6.0-6.5
Various Small Scale Hydro Projects 2 13 6.0-6.5
Unknown Wind Farm 1 Stage 1 75 6.9
2014 Various Cogeneration / Other 30 6.5-7.0
Various Small Scale Hydro Projects 3 13 6.5-7.0
Various Geothermal Expansion 20 6.5-7.0
Unknown Wind Farm 2 25 7.0
2015 Various Cogeneration / Other 10 7.0-7.5
Various Geothermal Expansion 10 7.0-7.5
Various Small Scale Hydro Projects 4 13 7.0-7.5
Unknown Wind Farm 1 Stage 2 75 6.9
Unknown West Coast Coal Plant 50 7.4
2016 Various Cogeneration / Other 10 7.0-7.5
Various Geothermal Expansion 10 7.0-7.5
2017 Various Cogeneration / Other 10 7.0-7.5
Various Geothermal Expansion 10 7.0-7.5
Unknown Southland Lignite Plant 200 7.4
2018 Various Cogeneration / Other 10 7.0-7.5
Various Geothermal Expansion 10 7.0-7.5
2019 Various Cogeneration / Other 10 7.0-7.5
Various Geothermal Expansion 10 7.0-7.5
2020 Various Cogeneration / Other 10 7.0-7.5
Various Geothermal Expansion 10 7.0-7.5
  • Geothermal projects totalling 210MW have been included at regular intervals over the period to 2020;
  • Two wind farms, in addition to those committed or "highly likely", totalling 175MW have been included over the period to 2020;
  • Stage I of Project Aqua is commissioned progressively with turbines 1-3 during 2008 and 2009;
  • Stage II of Project Aqua is commissioned progressively with turbines 4-6 during 2010 and 2011;
  • During the commissioning of Project Aqua other projects have been restricted to a few small cogeneration and geothermal developments;
  • Two coal-fired power stations in the South Island come on stream towards the end of the period.

The output of this scenario for a relatively dry year is illustrated in the quarterly supply/demand projection contained in Figure 6. For this illustration we have chosen the 2001 hydro inflow year which puts the power system under particular stress during the winter period.26

Figure 6: Dry Year Production - With Aqua Scenario

Figure - Dry Year Production - With Aqua Scenario

Full size image of Figure 6 available.

Figure 6 demonstrates that, in a dry year:

  • New Plymouth and Whirinaki are required to run reasonably significantly during 2004 and 2005;
  • Following the commissioning of e3p in 2006, less running of New Plymouth or Whirinaki is required;
  • This trend is emphasised during and following the progressive commissioning of Aqua from 2008 to 2011;
  • The "security of supply" criterion of "moderate" running of New Plymouth and/or Whirinaki is being achieved.

7.3 Without Aqua Scenario

The new generation investment schedule for the "without Aqua" scenario is outlined in Figure 7.

The following factors are worthy of note:

  • Several small hydro projects have been advanced and a total of 13MW more than in the With Aqua Scenario is included over the period to 2020;
  • Several small cogeneration projects have been advanced and a total of 70MW more than in the With Aqua Scenario is included over the period to 2020;
  • Several geothermal projects have been advanced and a total of 105MW more than in the With Aqua Scenario is included over the period to 2020;
  • The two wind projects have been advanced and a third project is included towards the end of the period;
  • The two coal fired power stations are advanced slightly and an additional 100MW has been included.
Figure 7: New Generation Investment Schedule - Without Aqua
Year Owner Scheme Rated Capacity (MW) Economic Haywards Price (c/kWh)
2003 Mighty River Power Rotokawa Geothermal Plant Expansion 4 Committed or Highly Likely
Auckland Hospital Coogeneration 5
2004 Trustpower Tararua Wind Farm Stage II 36
Government Whirinaki OCGT Dry Year Reserve 155
Genesis Power Huntly Gas Turbine 40
2005  Meridian Energy Manapouri Hydro Scheme Re-runnering 16
Genesis Power Hau Nui Wind Farm Expansion 8
Contact Energy Wairakei Geothermal Plant Expansion 10
Tuaropaki Trust Mokai Geothermal Plant Expansion 40
Meridian Energy Te Apiti Wind Farm 85
Various Cogeneration / Other 10
2006 Genesis Power Huntly e3p CCGT400 5.9
Top Energy Ngawha Geothermal Plant Expansion 20 5.5
Various South Island Hydro Efficiency Projects 20 5.0-6.0
Various Cogeneration/Other 10 5.0-6.0
2007 Various Small Scale Hydro Projects 1 8 5.0-6.0
Various North Island Hydro Enhancements 20 5.0-7.0
Various Cogeneration / Other 10 5.0-6.0
2008 Various Cogeneration / Other 10 5.0-6.0
Putauaki Trust Kawerau II Geothermal Plant 50 5.8
2009 Various Cogeneration / Other 20 60.-6.5
Various Geothermal Expansion 10 6.0-6.5
Various Small Scale Hydro Projects 2 13 6.0-6.5
2010 Various Cogeneration / Other 30 6.5-7.0
Various Small Scale Hydro Projects 3 13 6.5-7.0
Various Geothermal Expansion 20 6.5-7.0
Unknown Wind Farm 1 Stage 1 75 6.9
2011 Various Cogeneration / Other 20 7.0-7.5
Various Geothermal Expansion 20 7.0-7.5
Various Small Scale Hydro Projects 4 13 7.0-7.5
2012 Various Cogeneration / Other 20 7.0-7.5
Various Geothermal Expansion 20 7.0-7.5
Unknown Wind Farm 1 Stage 2 75 6.9
2013 Various Cogeneration / Other 20 7.0-7.5
Various Geothermal Expansion 20 7.0-7.5
Unknown Wind Farm 2 25 7.0
Unknown West Coast Coal Plant 50 7.4
2014 Various Cogeneration / Other 10 7.5-8.0
Various Small Scale Hydro Projects 5 13 7.5-8.0
Various Geothermal Expansion 15 7.5-8.0
2015 Various Cogeneration / Other 10 7.5-8.0
Various Geothermal Expansion 15 7.5-8.0
Unknown Southland Lignite Plant Stage 1 150 7.4
2016 Various Cogeneration / Other 10 7.5-8.0
Various Geothermal Expansion 15 7.5-8.0
2017 Various Cogeneration / Other 10 7.5-8.0
Various Geothermal Expansion 15 7.5-8.0
2018 Various Cogeneration / Other 10 7.5-8.0
Various Geothermal Expansion 15 7.5-8.0
Unknown Southland Lignite Plant Stage 2 150 7.4
2019Various Cogeneration / Other 10 7.5-8.0
Various Geothermal Expansion 15 7.5-8.0
2020 Various Cogeneration / Other 10 7.5-8.0
Variours Geothermal Expansion 15 7.5-8.0
Unknown Wind Farm 3 Stage 1 87 7.8

Figure 8 again demonstrates how supply is scheduled to meet demand in a dry year under this scenario. In particular, note that similar levels of dry year operation of New Plymouth and Whirinaki have been achieved in the two scenarios.

Figure 8: Dry Year Production - Without Aqua Scenario

Figure - Dry Year Productino - Without Aqua Scenario

Full size image of Figure 8 available.

7.4 Key Differences

The key differences between the scenarios are summarised in Table 9.

Table 9: Key Differences Between Scenarios
Plant Type Without Aqua  
Hydro Options generally advanced +13MW
Cogeneration Options generally advanced +70MW
Geothermal Options generally advanced +105MW
Wind Two projects advanced and a third included +87MW
Coal Two project advanced and additional capacity provided +100MW
  Total +375MW

It is worth noting here that Project Aqua's 524MW has been replaced with 375MW of alternative capacity, while maintaining a similar level of supply security. There are two reasons for this:

  • Some of the replacement projects are base-load in nature and are likely to provide more energy per MW than Project Aqua;
  • Apart from the small hydro options the replacement options are less dependent on inflows, providing an enhanced contribution, relative to Aqua, in a dry year.

Figure 9: Supply and Demand Balance Mean Year - Two Scenarios

Figure - Supply and Demand Balance Mean Year - Two Scenarios

Full size image of Figure 9 available.

These factors are highlighted by Figure 9, which demonstrates the balance between supply and demand achieved by each of the two scenarios (averaged across hydrology) relative to the current situation. It demonstrates that:

  • Following the commissioning of e3p in 2006 a slightly higher margin of supply over demand is maintained in both scenarios;
  • The without Aqua scenario achieves a similar level of dry year security while providing a lower average margin.


Back to Top