Christchurch stadium

Christchurch stadium

Welcome. This site was developed to keep residents, property and business owners, and interested Cantabrians informed about the, now completed, construction of Christchurch’s new stadium.

 

 

logo

[image] christchurch stadium.

 

Work in progress
View the latest images of the stadium construction.
View image gallery
Our partners
Addington venue
Key dates

The cost for constructing the temporary stadium is being funded by financial contributions from the Government and the Christchurch City Council, and will be supported by hire fees from sporting codes keen to use the venue (such as the Canterbury Rugby Union and the New Zealand Rugby Union). The stadium is also being built on land offered to the city by the Christchurch City Council.

Sponsorship opportunities are also available for corporates and suppliers of goods and services to the stadium.

We thank our immediate commercial and residential neighbours, including Addington Raceway and CBS Arena, for their encouragement and patience as dirty and noisy construction work gets underway.

The devastating earthquakes of 2010 and 2011 left Christchurch without a venue to host large outdoor sporting and music events over the short to medium term.

Following a review of other venues Addington was considered the most suitable (available) location for the new stadium. The Addington venue has been used for A&P shows and rugby matches in the past, and already had open space zoning. Canterbury Rugby League kindly agreed to surrender their lease of the old Rugby League Park to allow the new stadium project to proceed.

 

End March 2012

Planned opening of Christchurch Stadium

February 2012

Earthworks, ground improvements finished. The concrete foundations for the North, South and West Stands are to be completed. The four lighting towers are expected to be erected by the end of February. The seating areas and fabric roof sections in the North and South stands are being installed. Corporate suite portacoms are being custom-made off site at the moment. Food and Beverage portacoms from Eden Park are also being reconditioned before they too can be transported to the site for installation.

January 2012

Demolitions works complete. Earthworks and ground improvements made to prepare site for building, foundations built for lighting towers and drainage works done. Turf being laid from AMI and sports lights from Carisbrook are being remodeled for installation.

December 2011

Site blessed and 4 lighting towers recycled from Carisbrook were trucked up from Dunedin. Hawkins appointed as the main contractor in charge of construction.

November 2011

Demolition work began on the Addington site of the former Rugby League Park to remove two old stands ancillary buildings, lights towers, embankments and concrete bleacher seats.